US-backed consortium proposes $4.4bn LNG terminal and pipeline for Pakistan
The plan for Port Qasim would give Pakistan its first large onshore LNG storage, weeks after a Qatari-linked venture walked away from a smaller terminal.
ISLAMABAD — A consortium of US-linked companies has proposed investing up to $4.4 billion in an import terminal, storage tanks and a cross-country pipeline for liquefied natural gas in Pakistan, a project that would reshape how the country brings in the fuel.
The plan, first reported by Dawn at the start of November, centres on Port Qasim near Karachi. Officials at Pakistan's maritime affairs ministry say the consortium has asked the Port Qasim Authority for permission to carry out a preliminary study.
Two phases
The first phase, estimated at $1.7 billion, would build an LNG import terminal with four storage tanks and a throughput of about 35 billion cubic feet a year. It would be Pakistan's first large-scale onshore LNG storage facility; the country currently relies on floating terminals.
The second phase would lay a pipeline of about 1,100 kilometres, 42 to 48 inches in diameter, to carry around 1.2 billion cubic feet of gas a day to inland markets, bringing the total cost to $4.4 billion. The gas would be sold directly to large industrial and power customers rather than only through state utilities.
The proposal has been accepted for consideration under the project preparation programme of the US Trade and Development Agency. The sponsors are expected to look for financing from the US International Development Finance Corporation, with possible guarantees from the US Export-Import Bank.
A crowded field, and a costly winter
The plan surfaced days after Energas, a venture of QatarEnergy and Pakistan's Lucky Group, said it was abandoning a planned $150 million terminal at the same port after years of delays, citing changes in Pakistan's energy policy and unresolved fiscal issues.
The timing matters. Disruption to Qatari supplies has pushed up spot prices, and industry estimates suggest Pakistan may need to spend more than $1 billion to secure enough LNG for the coming winter. A large storage terminal would give the country more room to buy when prices are low, though the project still needs government approvals, financing and long-term customers before construction can begin.
This report draws on reporting by Dawn, Arab News and Oilprice.com.